Aquatic Center Updates

For periodic aerial footage of the construction site, visit the Springville City Vimeo page here.

May 2 , 2017

April 14, 2017

April 7, 2017

March 31, 2017

 

March 22, 2017

March 17, 2017

The blocks that they gym bleachers will be installed on have been installed. Walls are going up and the cement for floors is being poured. Things are moving forward at a great pace.

March 9, 2017

With multiple trades working there were 50+ employees on the site per day. The gym floor was completely poured yesterday along with some other footings. There is another pour today at 2 pm and 1 pm tomorrow. A total of 240 yards of concrete were poured this week.

In about two weeks, all footings will be poured. One week later all foundation will be complete (except where they are leaving an opening to get big equipment in and out of the facility to work). Veneer will be complete on the gym next week. The mason will start putting block up in Area 2 (pools) on April 3.