Aquatic Center Updates

For periodic aerial footage of the construction site, visit the Springville City Vimeo page here.

February 17. 2017

The walls have been going up quickly. Things are starting to take shape. Footings for other walls have been formed and those walls should be going up soon as well.

February 9, 2017

The crane arrived this week, was mobilized and it is being used to help the brick mason to start building the walls.

February 2, 2017

Footings have all been poured and the foundations wall is half done. The Mason should be able to start going vertical with the walls beginning in the Northwest corner of the building next week. Work has also been done on the water main vault, chemical room, interior wall footings and other parts of the building.

January 24, 2017

Footings and foundations are being poured on the West side working towards North corner and continuing East. Once they get the foundations in the Mason will be onsite to start going vertical with walls.