Aquatic Center Updates

For periodic aerial footage of the construction site, visit the Springville City Vimeo page here.

March 22, 2017

March 17, 2017

The blocks that they gym bleachers will be installed on have been installed. Walls are going up and the cement for floors is being poured. Things are moving forward at a great pace.

March 9, 2017

With multiple trades working there were 50+ employees on the site per day. The gym floor was completely poured yesterday along with some other footings. There is another pour today at 2 pm and 1 pm tomorrow. A total of 240 yards of concrete were poured this week.

In about two weeks, all footings will be poured. One week later all foundation will be complete (except where they are leaving an opening to get big equipment in and out of the facility to work). Veneer will be complete on the gym next week. The mason will start putting block up in Area 2 (pools) on April 3.

February 17. 2017

The walls have been going up quickly. Things are starting to take shape. Footings for other walls have been formed and those walls should be going up soon as well.

February 9, 2017

The crane arrived this week, was mobilized and it is being used to help the brick mason to start building the walls.

February 2, 2017

Footings have all been poured and the foundations wall is half done. The Mason should be able to start going vertical with the walls beginning in the Northwest corner of the building next week. Work has also been done on the water main vault, chemical room, interior wall footings and other parts of the building.

January 24, 2017

Footings and foundations are being poured on the West side working towards North corner and continuing East. Once they get the foundations in the Mason will be onsite to start going vertical with walls.